Lakehaven Phase 1 MBR WWTP Concrete

DCIM100MEDIADJI_0632.JPG

OWNER
City of Farmersville

ENGINEER
Kimley-Horn

COMPLETION DATE
February 16, 2024

AMOUNT
2,451,044.16

Project Details

Scope of Work of the Contract includes installing concrete, and providing all labor and materials required for an MBR basin, anoxic basin, anaerobic basin, aerobic basin, associated equipment pads, electrical pad, generator pad, and flatwork associated with the concrete package for Lakehaven Phase I MBR Wastewater Treatment Plant.