Cadiz and Y-Inlet Improvements

feature

OWNER
City of Dallas

ENGINEER
JQ Infrastructure, LLC

COMPLETION DATE
December 2020

AMOUNT
13,291,400

Project Details

  1. Inspection and repair of the 60-in West Bank Force Main at the west side of the Riverfront Boulevard and Cadiz Street intersection.
  2. Installation of the Cadiz Siphon RTU and termination of the wires at the East Bank-West Bank Siphon Interceptor.
  3. Construction of the 30-in and 42-in Line Z sanitary sewer south interceptor.
  4. Construction of Bypass Pump Stations No. 1 on the existing 90-in East Bank Interceptor, with a capacity of 130 MGD, No. 2 on the existing 51-in and No. 3 on the existing 54-in sanitary sewer lower north interceptor, with capacities of 20 MGD.
  5. Installation and operation of bypass pumping to divert flow from the 90-in East Bank interceptor and the 51 and 54-in lower north interceptors.
  6. Structural rehabilitation of the Y-Inlet structure at Cadiz Pump Station.
  7. Refurbish five (5) pumps and motors at the Cadiz Pump Station.
  8. Electrical improvements at the Cadiz Pump Station.
  9. Provide and install a new PLC (LPU-D1) inside the Cadiz Pump Station within the existing enclosure. Includes startup and testing of the LPU-D1.